Lagoon Expansion
In progressExpanding the City's wastewater lagoon system to add treatment capacity for current and future needs.
In progress Updated November 2026 Target completion: July 31, 2027
At a glance
Overall progress
8% complete
As of October 20, 2026, measured by quantities of work in place. The project is in its early stages — site mobilization and earthwork.
Milestone snapshot
0 of 7 milestones complete In progress: Lagoon earthwork Next: Lagoon piping and structure — target to be set
Latest update
October 2026 Site mobilization, earthwork, and erosion control underway; backfill placement for the treatment-cell berms and liner beginning. About 8% complete by quantities.Newest
About this project
- Three new treatment cells (Cells 1, 2, and 3) — the 2024 lagoon improvements
- A new constructed treatment wetlands
- Replacement of the dump station and lift station
- Existing lagoons repurposed to provide emergency storage
- Land reserved for a projected 40-year future lagoon expansion
- Official project name
- 2024 WWTF Expansion Project
- Project type
- Wastewater treatment facility (lagoon) expansion
- Funding
- USDA Rural Development
- Engineer
- BG Consultants
- Contractor
- Double S Dirt Works
- Construction start
- September 2026