Lagoon Expansion
In progressMilestone schedule
The project's key construction milestones, start to finish. Completed milestones show the date finished; the one in progress and the upcoming ones show their target completion date from the construction contract.
- Lagoon earthwork Target to be set In progress
- Lagoon piping and structure Target to be set Upcoming
- Lagoon testing Target: February 1, 2027 Upcoming
- Wetlands earthwork, piping, and structure Target: April 2, 2027 Upcoming
- Lift station Target to be set Upcoming
- Substantial completion Target: July 6, 2027 Upcoming
- Final completion Target: July 31, 2027 Upcoming
- Completed (date = completed)
- In progress
- Upcoming (date = contract target)
“Substantial completion” is when the project is finished enough to be put into use; “final completion” is when all remaining work, testing, and site cleanup are done.