City Projects

Lagoon Expansion

In progress

Milestone schedule

The project's key construction milestones, start to finish. Completed milestones show the date finished; the one in progress and the upcoming ones show their target completion date from the construction contract.

  1. Lagoon earthwork Target to be set In progress
  2. Lagoon piping and structure Target to be set Upcoming
  3. Lagoon testing Target: February 1, 2027 Upcoming
  4. Wetlands earthwork, piping, and structure Target: April 2, 2027 Upcoming
  5. Lift station Target to be set Upcoming
  6. Substantial completion Target: July 6, 2027 Upcoming
  7. Final completion Target: July 31, 2027 Upcoming

“Substantial completion” is when the project is finished enough to be put into use; “final completion” is when all remaining work, testing, and site cleanup are done.