City Projects

Water System Modernization

In progress

Retiring the old plant, purchasing treated water from the City of La Cygne, a new water tower, and expanding distribution lines to more homes.

In progress Updated October 2026 Target completion: April 2027
At a glance
Time-sensitive

No closures or shutoffs scheduled right now

Check back — this list updates as work is scheduled.

See all closures & shutoffs on Construction →
Resident action

Construction affecting your property or street?

Report it on the Construction tab so the City can track and follow up.

Report a water-project issue →

Overall progress

69% complete

69% complete · slightly behind the 73% pace mark

As of September 30, 2026, by construction value. Target completion remains April 2027.

Behind pace — target unchanged

Milestone snapshot

4 of 7 milestones complete In progress: Phase 2 — distribution lines and meters underway Next: Distribution main complete — target by April 10, 2027

Latest update

October 2026 About 69% complete overall, slightly behind the pace mark. Phase 1 (transmission main, booster station, fill station) is about 99% complete and in final punch-list; Phase 2 (distribution lines & meters) is about 64% complete, with crews on Applewood Ln, Rose Marie Dr, Camp Fire Dr, and Deepwoods Dr, and new meters going in around Kansas, Oklahoma, Ohio, and Iowa Dr. Lines near Knutt, Maple, Sycamore, Spruce Dr, and Meadowbrook passed testing and are now in service (9 new meters). Target completion remains April 2027.Newest
Next progress meeting: Monday, November 23, 2026