Lagoon Expansion

In progress

Recent updates

Progress on the lagoon expansion, newest first. To get updates as they're posted, sign up for alerts.

  1. October 2026 Site mobilization, earthwork, and erosion control underway; backfill placement for the treatment-cell berms and liner beginning. About 8% complete by quantities. In progress
  2. September 2026 Construction began. Crews stripped and stockpiled topsoil ahead of excavation. Done
  3. June 2026 Notice to proceed issued following USDA review. Done
  4. February 2026 Notice of award issued to the contractor, Double S Dirt Works. Done

From the October 26 progress meeting

  • Construction is about 8% complete, measured by quantities of work in place, as of October 20, 2026. The project is in its early stages.
  • Crews have mobilized to the site and are doing earthwork and erosion control. Backfill placement for the treatment-cell berms and liner is beginning, on schedule.
  • There have been no change orders, and the project engineer reported no outstanding observations or requests for information.
  • The contractor's first pay application — $256,650 — goes to the City Council for approval at its November 9, 2026 meeting.
  • The next progress meeting is Monday, November 23, 2026.
Next progress meeting: Monday, November 23, 2026