Lagoon Expansion
In progressRecent updates
Progress on the lagoon expansion, newest first. To get updates as they're posted, sign up for alerts.
- October 2026 Site mobilization, earthwork, and erosion control underway; backfill placement for the treatment-cell berms and liner beginning. About 8% complete by quantities. In progress
- September 2026 Construction began. Crews stripped and stockpiled topsoil ahead of excavation. Done
- June 2026 Notice to proceed issued following USDA review. Done
- February 2026 Notice of award issued to the contractor, Double S Dirt Works. Done
From the October 26 progress meeting
- Construction is about 8% complete, measured by quantities of work in place, as of October 20, 2026. The project is in its early stages.
- Crews have mobilized to the site and are doing earthwork and erosion control. Backfill placement for the treatment-cell berms and liner is beginning, on schedule.
- There have been no change orders, and the project engineer reported no outstanding observations or requests for information.
- The contractor's first pay application — $256,650 — goes to the City Council for approval at its November 9, 2026 meeting.
- The next progress meeting is Monday, November 23, 2026.