Water System Modernization
In progressEverything about active construction: upcoming closures and shutoffs, how to report a concern, where crews are working now, and project quick facts. For overall progress and the latest update, see the Overview.
Construction phases
Upcoming road closures & water disruptions
Short-term closures and brief water shutoffs happen as new lines are tied in. This list is updated as work is scheduled — check back before you head out, or sign up for alerts.
No closures or disruptions are scheduled right now. Check back, or sign up for alerts to get a notice as soon as one is posted.
Report a water-project issue
Is construction affecting your property, street, water service, or access? Report it here so the City can document the location, assign it to the appropriate person, and follow up.
For active flooding, a complete loss of water service, or another urgent hazard, call 913.757.2926.
Facebook comments and posts are not monitored as service requests. Please use this form or call City Hall so your concern can be tracked.
Reported concerns
See where water-project concerns have been reported and where they stand. The map shows active concerns by default — use its controls to view resolved or all. Pin locations are approximate, and no names or addresses are shown.
Where we're working
This map shows construction status across the community, updated after each progress meeting. Find your street to see where it stands.
Open the full-size map (PDF) for the most detail.
What's happening now
Active construction areas
- New lines Applewood Ln, Rose Marie Dr, Camp Fire Dr, and Deepwoods Dr — pipe installation underway
- Metering Kansas Dr, Oklahoma Dr, Ohio Dr, and Iowa Dr — new meters being set
- Now in service Knutt, Maple, Sycamore, and Spruce Dr, plus Meadowbrook — passed testing (9 new meters)
Cleanup & restoration
The contractor has committed to completing cleanup and restoration within 60 days after a line goes live — installed, metered, tested, and carrying city water.
The project team is tracking site-condition and cleanup items street by street.Quick facts
- Funding
- USDA Rural Development
- New water source
- Purchased from the City of La Cygne
- Storage
- New water tower (KDHE permit Mar 2, 2026)
- Metering
- ≈830 units
- Target completion
- April 2027