Water System Modernization

In progress

Everything about active construction: upcoming closures and shutoffs, how to report a concern, where crews are working now, and project quick facts. For overall progress and the latest update, see the Overview.

Construction phases

  • Phase 1 — Water source & storage 99%
    Transmission main from La Cygne, booster station, and bulk water fill station — final punch-list and walkthrough underway.
  • Phase 2 — Distribution system 64%
    New neighborhood water lines and meters to homes — roughly 830 meters total.

Upcoming road closures & water disruptions

Short-term closures and brief water shutoffs happen as new lines are tied in. This list is updated as work is scheduled — check back before you head out, or sign up for alerts.

No closures or disruptions are scheduled right now. Check back, or sign up for alerts to get a notice as soon as one is posted.

Report a water-project issue

Is construction affecting your property, street, water service, or access? Report it here so the City can document the location, assign it to the appropriate person, and follow up.

For active flooding, a complete loss of water service, or another urgent hazard, call 913.757.2926.

Facebook comments and posts are not monitored as service requests. Please use this form or call City Hall so your concern can be tracked.

Reported concerns

See where water-project concerns have been reported and where they stand. The map shows active concerns by default — use its controls to view resolved or all. Pin locations are approximate, and no names or addresses are shown.

Where we're working

This map shows construction status across the community, updated after each progress meeting. Find your street to see where it stands.

Construction progress map of Linn Valley showing waterlines by status: in service, installed but not yet active, under construction, and upcoming. Updated October 27, 2026.
In service Installed, not yet active Under construction now Upcoming (2–3 weeks)

Open the full-size map (PDF) for the most detail.

What's happening now

Active construction areas

  • New lines Applewood Ln, Rose Marie Dr, Camp Fire Dr, and Deepwoods Dr — pipe installation underway
  • Metering Kansas Dr, Oklahoma Dr, Ohio Dr, and Iowa Dr — new meters being set
  • Now in service Knutt, Maple, Sycamore, and Spruce Dr, plus Meadowbrook — passed testing (9 new meters)

Cleanup & restoration

The contractor has committed to completing cleanup and restoration within 60 days after a line goes live — installed, metered, tested, and carrying city water.

The project team is tracking site-condition and cleanup items street by street.

Quick facts

Funding
USDA Rural Development
New water source
Purchased from the City of La Cygne
Storage
New water tower (KDHE permit Mar 2, 2026)
Metering
≈830 units
Target completion
April 2027