Water System Modernization
In progressProject updates
-
March 2, 2026
KDHE water-tower permit received
The City received its Kansas Department of Health and Environment (KDHE) permit for the new water tower on March 2, 2026 — a key milestone toward putting the tower into service for storage and steady system pressure. A change order adding flush hydrants at dead-end lines was also submitted to USDA Rural Development for approval.
-
January 31, 2026
Booster station and transmission main complete
Construction of the transmission main and booster station is complete, with finish grading underway and the SCADA control system being brought online. Overall project progress was estimated at about 43% as of the end of January.
-
December 19, 2025
Water valves opened and pump start-up
Water valves were opened in mid-December, followed by scheduled pump start-up with the contractor. This set the stage for filling the new water tower and disinfecting the system in early 2026.