City Projects

Water System Modernization

In progress

Recent updates

Progress on the Water System Modernization project, newest first. To get updates as they're posted, sign up for alerts.

  1. October 2026 About 69% complete overall, slightly behind the pace mark. Phase 1 (transmission main, booster station, fill station) is about 99% complete and in final punch-list; Phase 2 (distribution lines & meters) is about 64% complete, with crews on Applewood Ln, Rose Marie Dr, Camp Fire Dr, and Deepwoods Dr, and new meters going in around Kansas, Oklahoma, Ohio, and Iowa Dr. Lines near Knutt, Maple, Sycamore, Spruce Dr, and Meadowbrook passed testing and are now in service (9 new meters). Target completion remains April 2027. In progress
  2. March 2026 The City received its KDHE permit for the new water tower on March 2, 2026 — a key step toward putting the tower into service for storage and steady pressure. Done
  3. January 2026 The transmission main from La Cygne and the booster station were finished, with finish grading underway and the SCADA control system coming online. Overall progress was about 43% at the end of January. Done
  4. December 2025 Water valves were opened in mid-December, followed by scheduled pump start-up with the contractor — setting the stage for filling the new water tower and disinfecting the system. Done
  5. June 2025 Notice to proceed issued. The contractor mobilized and construction began on the Water System Modernization project. Done

From the October 26 progress meeting

  • The project is about 69% complete overall (as of September 30) and is tracking slightly behind schedule — about 73% of the project's days have been used. Target completion remains April 30, 2027.
  • Phase 1 — the transmission main, booster station, and fill station — is about 99% complete and in its final punch list (installing the fill-station bollards and valve-top lids).
  • Phase 2 — distribution lines and meters — is about 64% complete. Crews are installing new lines on Applewood Ln, Rose Marie Dr, Camp Fire Dr, and Deepwoods Dr, and setting new meters around Kansas, Oklahoma, Ohio, and Iowa Dr. Lines near Knutt, Maple, Sycamore, and Spruce Dr and Meadowbrook have passed testing and are going into service (9 new meters).
  • The contractor has committed to completing cleanup and restoration within 60 days after a line goes live — installed, metered, tested, and carrying city water.
  • The next progress meeting is Monday, November 23, 2026.
Next progress meeting: Monday, November 23, 2026